by Paul Brinkmann Washington DC (UPI) Nov 15, 2021
Despite U.S. goals to land people on the moon again by 2024, delays of several years are likely, according to a NASA watchdog audit released Monday. Former Vice President Mike Pence set that 2024 goal in a 2019 speech, giving NASA just five years to accomplish the feat. While NASA reinforced the practicality of that goal for a long time, NASA Administrator Bill Nelson said Tuesday that the agency now plans to aim for 2025 because of funding shortfalls. But the new audit from NASA's Office of Inspector General dashed the 2025 goal as unrealistic. "Given the time needed to develop and fully test the [Human Landing System] and new spacesuits, we project NASA will exceed its current timetable for landing humans on the Moon in late 2024 by several years," the Office of Inspector General said. The audit pins blames space agency management for the delays, as well as the COVID-19 pandemic, which interrupted work on NASA's moon rocket, and on "significantly less" congressional funding than NASA sought. The agency requested $3.4 billion this year for the lunar Human Landing System program, but the Congress appropriated just $850 million. NASA awarded a contract to its lowest bidder, Elon Musk's SpaceX, to develop such a lander for $2.9 billion over the next few years. The audit recommends that NASA develop a "realistic, risk-informed schedule" that includes potential delays to better align expectations with the development schedule for rockets, capsules, spacesuits and other systems. The inspector general, Paul K. Martin, also recommended with his staff that NASA develop an Artemis-wide mission cost estimate and update it on an annual basis, and maintain an accounting of per-mission costs. In its official response, the space agency said it didn't agree with those two recommendations. NASA said it already follows its policies regarding cost estimates and argued that Artemis is a campaign, "and not an agency-defined program with a specific set of content or a period of time." Regarding mission costs, NASA argued in its response to the inspector report that it "does not account, track or report costs on a per-mission basis ... because doing so would reduce contractual transparency to key stakeholders." The agency didn't explain in its response who those stakeholders are. "Breaking out costs to align by mission may lead to inefficiencies ... and may dis-incentivize contractors to continue innovating," NASA said in its response. Jeff Bezos' Blue Origin filed formal protests and a lawsuit against NASA's award to SpaceX for the landing system, but a judge dismissed that suit Nov. 4. Meanwhile, on Sept. 14, NASA awarded a new round of $146 million to five U.S. companies, including Blue Origin and SpaceX, to continue development of lunar landers for astronauts.
Eagles complete CubeSat construction; next stop: the Moon Daytona Beach FL (SPX) Nov 15, 2021 In preparation for an upcoming moon mission, a team of engineers at Embry-Riddle Aeronautical University has completed construction of a miniature satellite camera system. The CubeSat, known as EagleCam, is en route to Intuitive Machines' headquarters, in Houston, Texas, this week where it will be integrated onto the Nova-C Lunar Lander spacecraft ahead of its scheduled mission to the moon in early 2022. EagleCam will take the world's first third-person shot of a spacecraft as it makes an extrater ... read more
|
|||||||||||||
|
|
| The content herein, unless otherwise known to be public domain, are Copyright 1995-2024 - Space Media Network. All websites are published in Australia and are solely subject to Australian law and governed by Fair Use principals for news reporting and research purposes. AFP, UPI and IANS news wire stories are copyright Agence France-Presse, United Press International and Indo-Asia News Service. ESA news reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. All articles labeled "by Staff Writers" include reports supplied to Space Media Network by industry news wires, PR agencies, corporate press officers and the like. Such articles are individually curated and edited by Space Media Network staff on the basis of the report's information value to our industry and professional readership. Advertising does not imply endorsement, agreement or approval of any opinions, statements or information provided by Space Media Network on any Web page published or hosted by Space Media Network. General Data Protection Regulation (GDPR) Statement Our advertisers use various cookies and the like to deliver the best ad banner available at one time. All network advertising suppliers have GDPR policies (Legitimate Interest) that conform with EU regulations for data collection. By using our websites you consent to cookie based advertising. If you do not agree with this then you must stop using the websites from May 25, 2018. Privacy Statement. Additional information can be found here at About Us. |